DIY drilling rig

However, if you really want to, you can save a lot on such an event by assembling a homemade drilling rig and doing the excavation work yourself. The manufacture of such a unit will require significant labor and time costs, but everything will more than pay off.

There are several types of homemade drilling rigs. Familiarize yourself with the key features of each existing option, choose the type of installation that best suits your application, and start assembling.


DIY drilling rig

Operating mock-up of “Drilling rig BU-3000 with simulation of rotary drilling and PO”

    December 28, 2014 17:26

The mock-ups demonstrate the filling capacity of the towers and demonstrate the operation of drilling at oil production sites.

The model of the oil rig BU 3000 is made in action; it shows the work of lowering and lifting pipes, as well as the drilling process. The movement of oil after production is also shown with a neon glowing cord.

  • : Scale 1:40. Dimensions: 1800x2000x350 mm Materials: PVC plastic, acrylic, vinyl film. Base: laminated chipboard (mahogany) - 100 mm. Painting: acrylic enamel Production time 25-30 days

Operating mock-up “Drilling rig BU-5000 with imitation of rotary drilling and rock drilling”

    December 28, 2014 17:25

The mock-ups demonstrate the filling capacity of the towers and demonstrate the operation of drilling at oil production sites.

The model of the oil rig BU 5000 is made in action; it shows the work of lowering and lifting pipes, as well as the drilling process. The movement of oil after production is also shown with a neon glowing cord.

  • : Scale 1:40. Dimensions: 1800x2000x350 mm Materials: PVC plastic, acrylic, vinyl film. Base: laminated chipboard (mahogany) - 100 Production time 25-30 days

The operating model of the “SKD-8 rocking chair with a geological section of the earth”

    December 28, 2014 17:23

Made in table-wall version

The model shows the surface and underground equipment of a deep-pumping well.

The layout demonstrates: the rocking structure, the main elements, the location and interaction of the main components in the process

installation operation; operation of the deep-rod pump valves in cycles. For a better overview of the pump operation there is a backlight.

The front panel of the model is a conventional section of a well with layers. The layers are colored in different colors according to the geological pattern of the soil.

Manufacturing of impact-type structures with electric drive

The supporting element of a homemade impact drilling rig with an electric drive is a frame structure. A three-phase asynchronous electric motor with a gearbox is used as a power device. To wind the cable, a drum is attached to the gearbox.


DIY drill from a shovel

Operating mock-up "Rocking chair SKD-8"

    December 28, 2014 17:22

The model demonstrates the operation of the equipment and all its component units

  • : Scale 1:10 Dimensions: 900 x 800 x 1000 mm. Materials: PVC plastic, acrylic. Base: laminated chipboard (mahogany). Painting: acrylic enamel. Production time 15 days

Operating layout of a "Coiled Tubing Unit"

    December 28, 2014 17:20

Made on the basis of a car.

The model shows the car and all the technological equipment installed on it: operator's cab,

drum with wound pipe, hydraulic system with hydraulic lift, centralizer of wound pipe, guide gander, shoe pipe feeder

into the well, preventer.

  • : Scale 1:15 Dimensions: 1230 x 500 x 770 mm. Materials: PVC plastic, acrylic, vinyl film. Base: laminated chipboard (mahogany) - 100 mm. Painting: acrylic enamel. Production time 20 days

Preparatory stage of pit construction

The top layer of soil is prone to crumbling, so the well is protected with a special structure - a pit, in other words, a hole one and a half by one and a half meters, the depth of which is no more than 2 meters. Boards are used to strengthen the walls, and they also line the floor. The strength of the floor depends on the thickness of the boards, so products no thinner than 5 cm are used. The pit is covered with a second flooring on top.

The holes for sand wells are small in size and are located at shallow depths, while the holes for artesian wells go several meters into the ground

Then prepare the holes in the following order:

  • erecting a drilling rig;
  • remove the top flooring;
  • find the center point on the lower flooring;
  • make a hole whose diameter coincides with the shoe and couplings;
  • cut out a second hole - in the upper flooring.

The vertical precision created by the two guide holes guarantees high-quality drilling.

Operating model “Operation of an oil field with four mechanized wells”

  • For: Rosneft December 28, 2014 17:19

The layout is made in a floor-standing version.

The model shows the Xmas tree used in the operation of 4 oil wells (mass flow, gas lift, rod pumps, rodless pumps).

The wells are shown in a cross-section showing the underground equipment of the well.

A well equipped with a rod pump shows a “pumping machine” installation, made in its current version.

The model of the rocking machine shows the structure and principle of operation of the units and the installation mechanism.

The model also shows the Sputnik oil metering station, an operator’s block with equipment installed in it, and a metering and switching installation with a bypass.

The front panel of the mock-up is painted in different colors – so-called layers in section.

  • : Scale 1:50. Dimensions: 2.0×1.0×0.6m Materials: PVC plastic, acrylic, vinyl film. Base: laminated chipboard (mahogany) - 100 mm, Cap: Plexiglas. Painting: acrylic enamel Production time 25 days

Screw MGBU

A do-it-yourself auger drilling rig is built around the main working element - the drill. To make it, you should use a steel pipe with a diameter of 10 cm. An external screw thread is installed at the upper end of the pipe. The opposite end is equipped with a screw screw, the diameter of which is approximately 20 cm. You can limit yourself to one or two turns in the screw. A pair of steel knives are welded to the ends of the auger so that when the pipe is installed in a vertical position, there is an angle between them and the horizontal surface.

To ensure more convenient rotation of the drill, you should weld another piece of pipe (about 1.5 m) and a tee with an internal screw thread. The tee is screwed onto a collapsible rod. Such a rod should also be 1.5 m in length.

The drilling rig consists of: 1 – drill; 2 – knob; 3 – tee; 4 – collapsible rod; 5 – couplings; b – tripods; 7 – holes; 8 – winches; 9 – gear.

The drill is deepened into the soil, followed by turning it three times, after which it is removed to remove loosened soil. These steps are repeated until the depth of the hole approaches one meter. After this, the rod must be extended. To do this, another part of the steel tube is mounted on it using a coupling. To make a well whose depth exceeds 8 m, you will have to secure the structure to a special tripod tower.

The upper part of this unit must have a hole through which the rod can move freely. Since the bar will become increasingly heavy, the use of a winch will be required to lift it. The tower can be made of either metal or wood.

Layout "Downhole drilling equipment"

    December 28, 2014 16:54

1. representation of the earth's surface in a section with a clearly expressed representation of the oil reservoir and various rocks, on the surface there is meadow grass and birch trees.

2. Downhole equipment is presented as a cross-section of a well (production string, tubing string, screw submersible pump (pump stator) on the tubing below, and a string of rods inside the tubing string with a rotor inserted into the pump stator). Stator in section, solid rotor with rotation of the rod string from the surface drive, with light indication of fluid flow from the formation to the surface (fluid flow from the formation along the internal part between the rods and tubing), anchor at the bottom of the pump, as a stop for the lower part of the tubing string into the production string .

§ Homemade winch and gear motor

When manufacturing a mini drilling rig, a “RA-1000” winch is used. You can take another one, but preferably one with a carrying capacity of at least 1 ton (or better yet, more). Some drillers install two winches, one electric and the other mechanical. In the case of a drill string wedge, it is very helpful.

To make the work easier, it is advisable to buy and connect two remote controls: one for reverse and engine speed, the other for the winch. This will save a lot of effort.

A gear motor for a homemade mini drilling rig will need 60-70 rpm, with a power of 2.2 kW. Weaker will not do. If you use a more powerful one, you will need a generator, since it will not be possible to connect to a voltage of 220 Volts. Recommended gear motor models for hydraulic drilling: 3MP 31.5/3MP 40/3MP 50.

Layout "Oil field arrangement scheme for production, metering, transportation of oil and gas"

    December 28, 2014 16:52

Made in a wall-mounted version in semi-volume. The model shows the entire volume of technological equipment used in the development of the oil field, as well as

oil supply and gas and water discharge lines.

The layout is electrified. Gas, oil, water lines completed

using the "running lights" method.

  • : Layout size 0.55x1.26x0.1m. Materials: PVC plates, plexiglass, Production time 15-20 days

What is a hand water pump

Having a source of water in your garden plot is the key to an excellent harvest. You also cannot do without it at home. However, water supply may be intermittent, and electricity supply in remote areas is unstable. In such conditions, it is necessary to purchase hand pumps for water at the dacha.

If you have shallow aquifers, you can drill a well yourself and become completely independent of the presence of an external water supply and poor-quality service from energy companies. The main thing is to choose the right hand pump for pumping water so that it gives maximum results with minimal investment and downtime for repairs and maintenance.

Layout “Installation for integrated oil and gas treatment”

    December 28, 2014 16:41

The layout is made in a floor-mounted version (possibly a wall-mounted version in a semi-volume)

The layout shows the technological complex of the arrangement

We are accepting applications

Apply now

For students in grades 1-11 and preschoolers

Description of the presentation by individual slides:

Creative project Topic: souvenir “Oil Rig” Completed by a student of grade 11 “A” of MAOU “School “Native Land”, Novy Urengoy Artur Zaretdinov Head: Ametov Mavlidin Zalimkhanovich technology teacher 2016

Selection and justification of the project New Year is coming - the time when relatives give each other gifts. I wondered what I could do to surprise mom and dad? They work for me in the oil and gas sector. After some thought, I decided to make a tabletop model of an oil rig with my own hands. Problem: choosing a gift for the New Year Relevance: for a gift, decorating the interior of a room or office. Practical significance: - for people working in the oil and gas sector; — for students of the oil and gas university, in order to make their dreams come true; — for people who want to expand their collection; - for use as office interior decoration.

Goal of the project The goal of the project is to make your own souvenir “Oil Rig. Dream come true"

Historical background Oil derrick of Colonel Drake, 1859, USA, Pennsylvania The first oil well in Russia (Grandmother-derrick) – Crimean region

Study and analysis of souvenirs Option 1 Option 3 Option 2

Selection of equipment and tools 1. Hacksaw. 2. Chisel. 3. Mallet. 4. Jigsaw. 5. Planer. 6. Wood lathe. 7. Drilling machine

§ Do-it-yourself drilling

To make a water well manually, auger or shock-rope technology is used. The hydraulic method will require a drilling rig. A collapsible model of a small-sized model can be made according to drawings from our website. And perhaps drilling water wells with your own hands will become your business.

Screw method

Working with an auger is the easiest manual method. It is used only to obtain shallow sources, the water from which will be used for technical purposes.

To perform independent drilling, you need a drill, which, when screwed into the ground, destroys the rock and grabs the soil with its blades. Periodic removal of the auger is necessary to clean it of sludge. This work is done without assistants.

In addition to the drill, you will need a tripod to which the auger is attached, and a lifting mechanism (manual with a winch or mechanized). Without these devices it is impossible to drill. Even several people will not be able to lift the drill with soil from a sufficient depth.

The greatest difficulty is drilling strictly vertically. Only a fixed drill will provide the necessary verticality, without which the pipes will be deformed. To ensure proper verticality, after passing 2 meters, you need to install a temporary metal pipe - a conductor, which will set the correct direction of movement.

A downhole conductor is an additional pipe with a larger diameter than the casing. The conductor in the upper part of the wellbore protects against wall collapse during drilling and does not allow surface water to pass through.

The auger method can be used in soft soils. If the auger hits a moraine, you will have to repeat the process in another place. Quicksand are also more difficult. Softened soil is difficult to pull to the surface. Only an auger with blades curved towards the top helps.

Shock-rope method

To make a source in clayey and loamy soils, it is better to use the shock-rope method. This method is more labor-intensive, but reliable and simple. For work, a drill glass is used - it is a cylinder with sharpened edges.

The essence of the method is to raise the glass (in other words, the cartridge) to the height from which it is dropped. Upon impact, the cylinder becomes clogged with soil. Raising the glass to the surface, remove excess soil.

The shock-rope method is good for almost all soils. But it takes a lot of effort, so hydraulic systems are often used to lift the cartridge.

Impact-rope technology is also good because it shows when water-bearing sand will appear. When reached, a bailer with a valve is used, capable of lifting liquefied soil.

A bailer is a hollow metal cylinder used to lift liquefied rock and mud from a well to the surface.